What the lights mean

What you seeWhat it means
Inverter light blinking yellowThe inverter is waiting to connect to the grid, connecting to REbus, or waiting to connect to REbus.
Inverter light solid yellowThe inverter is disabled or powering up.
Inverter light redThe inverter is overloaded or has a serious fault. Someone likely has to step in before it runs again.
Inverter light greenThe utility is connected and its voltage and frequency are normal.
Inverter light blinking greenThe inverter is in Island Mode because the utility service is interrupted.
Inverter light offThe inverter is powered down.
REbus light redA serious fault has been found on a device or on the REbus wiring.

Error codes that go with this problem

CodeWhat it means
Inverter shows Waiting, Standby or Low REbus VoltageThe inverter has not connected to the grid. Not an error. Expected for 5 minutes after the system is first set up or after a grid outage; otherwise usually a problem with the AC power.
Pattern lockoutOn inverter firmware 13853 this alternates with REbus under-voltage events during the 5 minute wait before the inverter connects to the grid. Later firmware shows Waiting instead.

What to check first

  1. Look at the inverter's status light and its screen, and note the light colour and the state shown.
  2. If the system was just set up or the power just came back, wait 5 minutes. The inverter waits that long before it connects to the grid.
  3. A red inverter light means an overload or a serious fault, and someone likely has to step in before it runs again. A red REbus light means a serious fault on a device or the REbus wiring.
  4. Call your installer if the inverter still shows Waiting, Standby or Low REbus Voltage after 5 minutes, or the inverter light is red. For those three states, the next steps are checking the grid profile and measuring the AC supply at the inverter.
Safety. The inverter shutdown and restart sequence is meant for trained, certified people only.